Our architect, Cyril Stewart, has sent a big roll of drawings to our contractor, Batten & Shaw, for bidding and an application for the permit. The drawings include details on landscaping, engineering work including structural, mechanical, plumbing, and electrical engineering, as well as interior design and finishes. Several subcontractors have already walked through the building to prepare submitting their bids.
Electrical engineering plans took a little longer than expected due to concerns about the location of our transformer that powers the entire facility. Thankfully, the transformer will not have to be moved.
Thorough testing revealed multiple areas with asbestos in tiles, adhesives, insulation, and finishes, and we are making plans to complete the necessary abatement work.
In a few weeks, we expect to have solid cost estimates for all parts of the project. In the meantime, our leadership has begun conversations about fundraising options we may include, both as a means to help offset the overall cost AND as a way to celebrate our bicentennial year and the memory of loved ones (like trees, personalized pavers, and artwork.)